CR-046 全鏈路

open

8 days late (10/17/2026)

AC 11 未閉環:待客戶主檔、card 權益來源、跨 JVM 端到端環境

100%

31 issues   (30 closed — 1 open)

Phase-1 文件基線與需求註冊

open

7 days late (10/18/2026)

GOV/BRD/SAD/SCS/SDD/CSP 等文件基線(已完成)

92%

152 issues   (135 closed — 17 open)

Backlog

open

待排入之增量與外部依賴

72%

35 issues   (25 closed — 10 open)

Phase-2 平台與基礎建設

open

WBS 階段 2(GOV-006 §1)

87%

31 issues   (23 closed — 8 open)

Phase-3 領域服務 R1

open

WBS 階段 3(GOV-006 §1)

99%

86 issues   (85 closed — 1 open)

Phase-4 領域服務 R2/R3 與參數極大化

open

WBS 階段 4(GOV-006 §1)

95%

121 issues   (109 closed — 12 open)

Phase-5 WebUI 作業台

open

WBS 階段 5(GOV-006 §1)

100%

19 issues   (19 closed — 0 open)

Phase-6 橫切品質關卡

open

WBS 階段 6(GOV-006 §1)

100%

10 issues   (10 closed — 0 open)

Phase-7 測試與 POC 驗收

open

WBS 階段 7(GOV-006 §1)

50%

17 issues   (0 closed — 17 open)